How-to MRP / MRP Execution

MRP Execution

Once the MRP has been set up it is possible to start running the MRP processes.

MRP のセットアップが完了させたら、MRP を実行する。

 In this example is created a Sales Order of USB cables and a Work Requirement for USB Cables that it is not enough to fulfill the Sales Order.

今回の例の Sales Order "USB cables" と Work Requirement "USB Cables" は Sales Order には十分ではない。

Insert demand見込み

Create and complete a Sales Order using a document type that does not generate the corresponding shipment, in this case is used the Standard Order and a Scheduled delivery date 2008-07-07. The order has a unique line for 500 USB Cables.

USB Cables を500本 見込む。









Create and process a Work Requirement for 100 Usb Cable. The three dates are the same 2008-08-05.







Manufacturing Plan

Create a new Manufacturing Plan.

  • Name: Manufacturing Plan 1
  • Document Date: 2008-06-15
  • Time Horizon: 60
  • Lead Time: 1
  • Planner: Planner 1

After processing the plan 10 lines are inserted in the Lines tab. We can see how it has considered the Sales Order, but not the Work Requirement because its Launch WR Date (2008-08-05) is later than the 30 days limit set in the Planning Method.